Dasu hydropower project, Pakistan
Name of the Project
Dasu hydropower project (HPP).
Location
The project is located on the Indus river, 7 km upstream of Dasun, in the district of Kohistan, Khyber Pakhtunkhwa, in Pakistan.
Client
Pakistan Water & Power Development Authority (WAPDA).
Project Description
The Dasu project is downstream of the proposed Diamer Basha dam site and will be a run-of-river operation and will have an installed capacity of 5 400 MW and provide energy of 21 700 GWh/y. The project will be built in two stages.
Stage 1 includes the construction of a roller-compacted concrete dam with appurtenant structures; an underground powerhouse with appurtenant structures; six turbogenerators with a total installed capacity of 2 160 MW; one double-circuit 500 kV transmission line; the relocation of the KKH (62 km), Colony and right bank access roads (81 km); and a 132 kV transmission line. Land acquisition, resettlement and environmental and social management will also be pursued.
Stage 2 includes the construction of an underground powerhouse and appurtenant structures; the installation of nine turbogenerators with a total capacity of 3 240 MW units; and one double-circuit 765 kV transmission line.
The operation will have a gross storage capacity of 1.41-billion cubic metres and live storage capacity of 820-million cubic metres.
Jobs to Be Created
Not stated.
Value
Not stated.
Duration
The project is expected to be completed in March/April 2023.
Latest Developments
The WAPDA has awarded China’s Zhongmei Engineering Group two contracts for resettlement works associated with the Dasu HPP
Key Contracts and Suppliers
China Gezhouba Group (main contractor) and Zhongmei Engineering Group (resettlement contract).
On Budget and on Time?
Not stated.
Contact Details for Project Information
Dasu HPP GM Abdul Zahir Khan Durrani, tel +92 42 9920 2676.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation