Cuxhaven wind turbine manufacturing facility, Germany

26th August 2016

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

  

Font size: - +

Name and Location
Cuxhaven wind turbine manufacturing facility, Germany.

Client
Siemens.

Project Description
The project involves the construction of a wind turbine manufacturing facility in Cuxhaven.

The plant will be located at the edge of the harbour and will have a surface area of 170 000 m2 – the size of about 24 soccer fields.

A poured concrete plate, 320 m long and more than 160 m wide will be held in place by 1 900 concrete piles and will form the base of the future production hall, which will be up to 30 m high. Once production begins, the ground must withstand heavy loads of up to several hundred tons.

Besides the assembly hall, a two-storey building with a useable area of about 3 800 m2 will be built, which will accommodate offices and a canteen, as well as a technological building and a gatehouse.

Value
€200-million.

Duration
Construction of the actual building was officially started by Siemens with a ground-breaking ceremony in the middle of June.

By mid-2017, the production of nacelles for the next-generation D7 wind turbines will have begun.

This will coincide with the start of the manufacturing of the 75 m rotor blades at the new plant in Hull, UK.

Latest Developments
One year after the initial investment decision, construction at the building site has started. Soil compaction and the preparation of the pile foundation, with 1 900 concrete piles, have already been completed.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
Not stated.

Contact Details for Project Information
Siemens, Bernd Eilitz, tel +49 40 2889 8842 and email bernd.eilitz@siemens.com.

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

Showroom

Multotec
Multotec

Multotec, recognised industry leaders in metallurgy and process engineering help mining houses across the world process minerals more efficiently,...

VISIT SHOWROOM 
Actom image
Actom

Your one-stop global energy-solution partner

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 19 April 2024
Magazine round up | 19 April 2024
19th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.176 0.24s - 159pq - 2rq
Subscribe Now