Court declares R2.5bn eNaTIS contract invalid
The high court in Pretoria has declared that the extension of the eNaTIS system contract from 2010 to 2015 by former transport department director-general George Mahlalela was invalid from the date of extension.
Tasima was awarded the tender to operate‚ manage and maintain the country’s vehicle registration system since 2002. From 2007‚ Tasima provided the service on a month-to-month basis because the department wanted to offer the service in-house‚ but Mahlalela in 2010 extended the agreement for another five years.
There had been a dispute about the extension of the contract by Mahlalela‚ but it had not been resolved when the contract expired on April 30.
Tasima approached the court this year in an effort to persuade the department to allow for a five-year phased transfer and handover of the eNaTIS system to the department.
However‚ the department wanted an immediate hand over and launched a counter-application to declare the contract Mahlalela signed in 2010 extending the contract invalid from the beginning.
In her judgment‚ Judge Wendy Hughes said there had been a material dispute since 2012 as to whether the agreement was amended and extended to April 30 2015.
Hughes said: “From the outset it is clear to me that Mahlalela did not adhere to section 217 (1) of the Constitution in that the extension agreement was not done in a fair‚ transparent‚ equitable and competitive and cost-effective manner.
“With regards to the cost-effective aspect‚ it is illustrated by (the transport department) that in the Mahlalela extension period‚ (Tasima) gained R2.5-billion whilst the initial contract was for R355-million inclusive of VAT.”
Another contract extension that Mahlalela signed‚ for the provision of driver licence cards with Prodiba‚ was declared invalid from the outset by the Supreme Court of Appeal in March this year.
Mahlalela signed the contract extension in February 2013 for a five year period beginning from March 2014.
Hughes said the transfer of the system from Tasima to the department could not be a lengthy process as the department had the benefit of running the eNaTIS system on a month-to-month basis from 2007 to 2010 and a further five years thereafter.
She ordered that the department request the transfer within five days of the date of the order‚ and that it be completed within 30 days of the request.
Transport Minister Dipuo Peters welcomed the court ruling and hailed it as victory for taxpayers. The department would not immediately say if it would claim the money back.
“The end of this tedious journey leaves us with several lessons with regard to prudent utilization of public funds. It also forces us to reflect on contract management‚ especially when it concerns contracts of this magnitude‚” Peters said.
Efforts to contact Tasima were unsuccessful.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation