Bosveld Phosphates Selati river pollution stopped

8th January 2014

By: Leandi Kolver

Creamer Media Deputy Editor

  

Font size: - +

Mining company Bosveld Phosphates on Thursday stated that a secondary leak of contaminated process water from its fertiliser manufacturing plant in Phalaborwa, Limpopo, into the Selati river, caused by a crack in the concrete storm water canal on site owing to water pressure, had been completely stopped on January 6, after it had been reduced to a trickle on January 1.

Prior to this leak having been discovered, the plant's impoundment dam had overflown on December 31, owing to exceptional rainfall in late December, also resulting in a spillage of contaminated process water into the Selati river for a brief period.

The company stated that its engineers had responded immediately to this, repairing the leak within 24 hours, and was confident that, owing to the very high dilution factor caused by strong flows in the Selati river and the Olifants river downstream, there would be no lasting harm to the environment.

However, the South African government news service on Tuesday reported that South African National Parks spokesperson Ike Phaahla said the environmental damage caused by the spill was "extensive and spreading".

“Dead fish have, thus far, been observed over a 15 km stretch. Some fish have been taken for autopsies to determine the cause of death and acid levels,” said Phaahla.

It was also reported that the Department of Water and Environmental Affairs had already taken administrative action and had laid criminal charges against Bosveld Phosphates for contravening the National Water Act.

Bosveld had been struggling with legacy water management challenges since acquiring the mothballed fertiliser plant from petrochemicals giant Sasol in October 2011, and started operations in early 2012.

“[This] challenge was compounded by the extraordinarily high rainfall in the Phalaborwa area over the past two years, exceeding the 1:50 year flood level in January 2012 and the 1:100 year flood level in January 2013, [which was] exacerbated by high rainfall in December 2013,” Bosveld said in a statement.

The company said it would continue with its efforts to put in place long-term corrective measures agreed in close consultation with external specialists and the relevant authorities.

Edited by Tracy Hancock
Creamer Media Contributing Editor

Comments

Showroom

Condra Cranes
Condra Cranes

ISO-certified Condra manufactures overhead cranes, portal cranes, cantilever cranes and crane components: hoists, drives, end-carriages, brakes and...

VISIT SHOWROOM 
Rio-Carb
Rio-Carb

Our Easy Access Chute concept was developed to reduce the risks related to liner maintenance. Currently, replacing wear liners require that...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 19 April 2024
Magazine round up | 19 April 2024
19th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.073 0.135s - 155pq - 2rq
Subscribe Now