Barakah nuclear power plant, United Arab Emirates – update

Image of the Barakah NPP

3rd March 2023

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Barakah nuclear power plant (NPP).

Location
The western region of the Emirate of Abu Dhabi, on the Arabian Gulf, in the United Arab Emirates (UAE).

Project Owner/s
Emirates Nuclear Energy Corporation (ENEC).

Project Description
The project involves the construction of the UAE’s first nuclear energy plant comprising four APR1400 nuclear reactors.

The APR1400 is a pressurised water reactor and every unit produces up to 1 400 MW of electricity. The reactors have an operational life span of 60 years.

When fully operational, the four units of the plant will produce 5.6 GW of electricity while preventing the release of more than 21-million tons of carbon emissions every year.

Potential Job Creation
ENEC’s workforce of more than 1 700 employees will increase to about 2 500 to operate and maintain the plant.

Capital Expenditure
The project is valued at about $20-billion.

Planned Start/End Date
Construction began on Unit 1 in July 2012, with grid connection achieved in August 2020 and full power in December 2020. In April 2021, Barakah Unit 1 was declared commercially operational.

Construction on Unit 2 started in May 2013 and was completed in July 2020; commercial operations started in March 2022.

Construction of Unit 3 started in September 2014 and that of Unit 4 in September 2015.

Latest Developments
The third unit at the Barakah NPP has been declared in commercial operation, less than a year after the second unit at the plant reached the same milestone.

The operation’s teams were able to shorten the time to reach commercial operations after fuel loading by using their experiences from the first two units.

Key Contracts, Suppliers and Consultants
Korean Electric Power Corporation (design, build and operate four 1 400 MW nuclear power reactors).

Contact Details for Project Information
ENEC, tel +971 2 659 5555 or email info@enec.gov.ae.

To watch Creamer Media's latest video reports, click here
 

Edited by Creamer Media Reporter

Comments

Showroom

VEGA Controls SA (Pty) Ltd
VEGA Controls SA (Pty) Ltd

For over 60 years, VEGA has provided industry-leading products for the measurement of level, density, weight and pressure. As the inventor of the...

VISIT SHOWROOM 
Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (26/04/2024)
26th April 2024 By: Martin Creamer
Magazine cover image
Magazine round up | 26 April 2024
26th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.092 0.164s - 163pq - 2rq
Subscribe Now