KALGOORLIE (miningweekly.com) – Gold hopeful Gryphon Minerals was hoping to pour its first gold at the Banfora project, in Burkina Faso, by the first quarter of 2016.
The ASX-listed junior on Monday revealed that the feasibility study into the project had revealed that a capital investment of $96.8-million would be required to sustain yearly gold production of some 70 000 oz over a nine-year mine life.
The Banfora project was expected to produce more than 80 000 oz for the first four years of its mine life, based on an ore reserve estimate of 17.4-million tonnes, grading 1.5 g/t gold for 826 000 oz of contained gold.
The feasibility study was based on a two-million-tonne-a-year heap leach operation, which was currently fully permitted, allowing for early site works to start.
The project was underpinned by Gryphon’s current cash and investment position of A$37-million, as well as a mandate with Macquarie Bank to secure up to $60-million in a senior loan facility.
The debt financing would be completed by the end of this quarter.
“Its an exciting time for Gryphon as we go from an explorer to early site work in this quarter, the start of the construction early next quarter, and commissioning of gold next Christmas,” Gryphon MD Stephen Parsons told delegates at the Diggers & Dealers conference on Monday.
Parsons noted that the cash flow generated from the heap leach operation would fund a carbon-in-leach (CIL) operation at Banfora, which would run in tandem with the heap leach processing, and would exploit the sulphide ounces directly below the heap leach pits.
Parsons said that an initial heap leach project was considered in favour of a CIL project, based on the high capital costs associated with a CIL operation.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation